Rehab Timeline

A summary of Meetinghouse Preservation an Accessibility projects over the past decadent beyond.

Historic Architect Hired: Formal Assessment & Multi-Year Plan Developed



Peeling Exterior Quickly Painted

— 2011

Critical Electrical and Structural Repairs Executed



Timber Frame Analyed and 3D Structural Drawings Developed

— 2012

Failing Tower Temporarily Reinforced


— 2013

FPC Internal Capital Campaign

Feasibility Study, extensive education, and successful raising of $800Kin multi-year pledges

.
— 2014

Unsafe Steeple Lowered



Preparations for Lifting the Building Underway

Continued into 2016; last service in Sanctuary was Easter 2016


— 2015

Decaying Steeple Disassembled and Transported for Off-Site Rehab



Building Lifted and New Foundation Poured



Floor and Lower Wall Timber Frame Rehabbed; Floors Leveled



Connector Foundation Poured and Shell Constructed



See:

— 2016

Tower Base Rehabbed

Included removing 1990s steel beams and anchors and installing two new 60’ tall corner posts


— 2017

Steeple Frame Rebuilt and Trim Reproduced

95% of the frame and trim ended up being reconstructed from matching new material

— 2018

Steeple Reconstructed and Copper Roofing Applied



Steeple Re-Installed



Tower Rehab and Painting Completed

— 2019

Connector Siding, Windows, Doors & Insulation Installed



Connector Exterior Painted



Elevator Installation Begun



— 2020

Connector Interior Finished



Elevator Finished



Meetinghouse Exterior Scraped and Painted

— 2021

Clock Mechanism Rehabbed and Clock Restarted



Sanctuary Rehabbed & Ready for Use by Church and Community



Lower Level Rooms Rebuilt and Open for Church and Community Use



Roof System Rehabbed



Landscaping Planned and Executed

— 2022+