Rehab Timeline

A summary of Meetinghouse Preservation an Accessibility projects over the past decadent beyond.

“

Historic Architect Hired: Formal Assessment & Multi-Year Plan Developed


Peeling Exterior Quickly Painted

”

— 2011
“

Critical Electrical and Structural Repairs Executed


Timber Frame Analyed and 3D Structural Drawings Developed


”
— 2012
“

Failing Tower Temporarily Reinforced


”
— 2013
“

Unsafe Steeple Lowered


Preparations for Lifting the Building Underway

Continued into 2016; last service in Sanctuary was Easter 2016


”

— 2015
“

Decaying Steeple Disassembled and Transported for Off-Site Rehab


Building Lifted and New Foundation Poured


Floor and Lower Wall Timber Frame Rehabbed; Floors Leveled


Connector Foundation Poured and Shell Constructed



See:

”
— 2016
“

Tower Base Rehabbed

Included removing 1990s steel beams and anchors and installing two new 60’ tall corner posts


”
— 2017
“

Steeple Frame Rebuilt and Trim Reproduced

95% of the frame and trim ended up being reconstructed from matching new material

”
— 2018
“

Steeple Reconstructed and Copper Roofing Applied


Steeple Re-Installed


Tower Rehab and Painting Completed

”
— 2019
“

Connector Siding, Windows, Doors & Insulation Installed


Connector Exterior Painted


Elevator Installation Begun


”
— 2020
“

Connector Interior Finished


Elevator Finished


Meetinghouse Exterior Scraped and Painted

”
— 2021
“

Clock Mechanism Rehabbed and Clock Restarted


Sanctuary Rehabbed & Ready for Use by Church and Community


Lower Level Rooms Rebuilt and Open for Church and Community Use


Roof System Rehabbed


Landscaping Planned and Executed

”
— 2022+